Licensed Builder: Rolesville North Carolina 27571

Metal Buildings For Businesses and Individuals

Timeline: Metal Building Construction | Red Iron 50x100

Production timeline for the turnkey construction of a 5000 square foot, 50x100 red iron pre-engineered metal building in Raleigh NC

Planning, designing, engineering, fabrication, and installation are all provided by Inco Steel Buildings, Inc.

2024 Timeline for professional metal building construction

UPDATE Winter Production Timeline 2026

UPDATE January 05, 2026

Taking the time to get a job right the first time is a hallmark of Inco Steel Buildings.

Each construction project is unique in its Variables and Complexities, and in its Building Owners, all of which impact the Production Schedule and the Completion Date Timeline

  • Weather Delay Allowance      2-Weeks
  • Building Permit Application    4-Weeks Minimum
  • Engineering the Steel Building System           4-Weeks
  • Steel Building System Manufacturing 14-Weeks
  • Engineering the Foundation System   4-Weeks
  • Delivery of Steel Package        1-Week
  • Scheduling of Trade Contractors         1-Week
  • Land Clearing Preparation of Pad and Staging Area   1-Week
  • Earthwork, Grading, Compacting of Building Pad      2-Weeks
  • Foundation Construction and Inspections      3-Weeks
  • Curing Of Foundation Concrete          4-Weeks Mandatory
  • Erect Steel Building Framing System  1-Week
  • Building Inspection by Municipality   1-Week
  • Window and Door Installation            1-Week
  • Metal Roofing, Metal Wall Panel Installation 1-2 Weeks
  • Close-out Phase of Contract   1-Week
  • Close-out of Jobsite and Clean-up      2-Weeks
  • Equipment, Container, Utilities Removal        1-Week

5000 Square Feet

Pre-Engineered Metal Building, Red Iron I-Beam Steel

Inco Steel Buildings, Inc provides [all] planning, design, engineering, fabrication and installation.
  • 50W x 100L x 16EH PEMB
  • Commercial Grade Steel Building
  • Clear Span.  Red Iron I-Beam Steel
  • 26-Gauge PBR Purlin Bearing Rib Panel
  • 12×14 Rollup Steel Sheet Doors
  • 3070 Steel Hollow Core Personnel Doors

Production Timeline

Red iron metal buildings have a wide range of factors that influence the production timeline when the job is well-planned, organized and erected by skilled professionals. 

Typical factors include the building size, and type, the complexity of the project, the delivery of special-order materials and products, weather conditions, the time of year building is being constructed, and building component specifications. 

Critical factors beyond Inco Steel Buildings, Inc control include the other parties’ timely decision-making, their cooperation during the entire process, their completion of land use and zoning approvals, and their scheduling and supply of land surveyor’s documents and plat plan during the pre-construction phase.

Detailed close-up of the U.S. Treasury text on a dollar bill, showcasing intricate design and financial symbolism.

PRICE INCREASE

Effective January 23, 2026.  Factory price increases of up to 12%