Timeline: 50x100 Red Iron Metal Building Construction

Turnkey Construction: 5,000 Square Foot Metal Building in Raleigh, North Carolina

Your Custom 5,000 Sq. Ft. Red Iron Building: The Step-by-Step Raleigh Construction Timeline

Building a 5,000 sq. ft. commercial space doesn’t have to be overwhelming. From initial land clearing to turnkey move-in, we manage every step of your custom red iron steel building project. Discover our streamlined Raleigh construction timeline and see how we bring your vision to life on time and on budget

Metal Building Construction Timeline

  • 50W x 100L x 16EH PEMB
  • Commercial Grade Steel Building
  • Clear Span.  Red Iron I-Beam Steel
  • 26-Gauge PBR Purlin Bearing Rib Panel
  • 12×14 Rollup Steel Sheet Doors
  • 3070 Steel Hollow Core Personnel Doors

6 to 8 Months Average

For a rectangular 5,000 sq ft red iron metal building (50x100x16), the total timeline from initial design to construction phase, to customer move-in is typically 6 to 8 months. While the actual metal erection (framing and sheeting) takes only 2 to 3 weeks, pre-engineering and manufacturing, and foundation system timelines influence the complete start-to-finish timeline.

PRODUCTION TIMELINE

E.G, 5000 SQ FT

Building Inspection (Municipal)

1-Week

Weather Delay Allowance

2-Weeks

Engineer Building System

2-4 Weeks

Engineer Foundation System

2-4 weeks

Building Permit Issuance

1 to 120 Days

Land Clearing

8-10 Days

Grade/Compact Cleared Land

7-8 Days

Building Pad Cut

1-5 Days

Deliver Steel Building Package

16-20 Weeks

Foundation Prep/Pour/Finish

1-2 Weeks

Foundation Curing Phase

4-Weeks Minimum

Erection Phase (5-6 Crewmembers)

2-3 Weeks

+ Add Interior Buildout Phase

+ Add 6-8 Months to Erection Phase

Close-Out Project Phase

2-3 weeks

Approx. Timeline

6 to 8 months*

  • Excludes Building Pemit

  • Excludes Interior Buildout/Finishing

Concept to Completion: The 7-Phase Steel Building Process in Raleigh NC
Stress-Free Organized Construction: Our 7-Phase Process from Concept to Completion

At Inco Steel Buildings, Inc, every step of the process is organized.  Nothing is missed, or left to chance.   Our metal building construction timeline can be structured chronologically into distinct phases: Grouping the timeline into these key categories ensures a highly scannable, logical workflow for your project.

Phase 1: Pre-Construction Planning

  • Land Surveying: Boundary Survey and Site Plan Drawing
  • Site Evaluation and Soil Bearing Analysis Testing
  • Define Project Needs and Design Specifications
  • Project Development and Conceptual Design
  • Zoning, and Regulatory Approvals
  • Building Permit Application
  • Budgeting and Timeline Estimation

Phase 2: Site Access and Road/Driveway

  • Entrance Building
  • Road and/or Driveway Building

Phase 3: Civil Work and Site Preparation

  • Site Clearing, Grubbing, Grading
  • Under Ground Drainage System Installation
  • Locate Utilities to the Job Site
  • Building Pad Excavation, Grading and Site Compaction

Phase 4: Fabrication & Delivery

  • Engineering and Drafting Steel Building
  • Engineering and Drafting Foundation System
  • Manufacturing the Structural Steel Components
  • Scheduling Structural Steel Material Delivery
  • Staging Materials on Site

Phase 5: Foundation and Site Preparation

  • Site Clearing and Grading
  • Running Utilities to the Job Site
  • Excavating and Pouring the Foundation
  • Mandatory Concrete Curing Time

Phase 6: Structural Erection

  • Set, Brace, and Bolt Steel Columns and Rafters
  • Set, Assemble and Bolt the Primary and Secondary Steel Framing
  • Install Insulation and/or Vapor Barriers
  • Install Wall and Roof Steel Sheeting

Phase 7: Finishing and Close-out

  • Install Doors, Windows, and Trim
  • Install Gutters and Downspouts
  • Final Inspections and Building Code Compliance
  • Project Closeout and Owner Handover
Determinants of Project Schedule Drivers

The production and erection timeline for red iron metal buildings depends on various factors, but careful planning and skilled professionals ensure a highly efficient process.

Controlling factors include the building size, and type, the complexity of the project, the delivery of special-order materials and products, weather conditions, the time of year building is being constructed, and building component specifications. 

Timeline Influencers, Dependencies and Risk

Critical factors beyond Inco Steel Buildings, Inc control include the other parties’ timely decision-making, their cooperation during the entire process, their completion of land use and zoning approvals, and their scheduling and supply of land surveyor’s documents and plat plan during the pre-construction phase.

  • The Builder’s performance of the Work is strictly contingent upon the Customer’s timely and diligent fulfillment of their obligations.

Critical factors beyond the Builder’s control include, but are not limited to:

  • (a) The Customer’s timely decision-making and written approvals (which shall be provided within (3) business days of a request by the Builder);
  • (b) The Customer’s active cooperation during the entire pre-construction and construction process;
  • (c) The Customer’s timely completion and procurement of all necessary land use, environmental, and zoning approvals; 
  • (d) The Customer’s timely scheduling, supply, and approval of all land surveyor’s documents and plat plans.
Timeline Extension

Project timelines are primarily adjusted to account for external dependencies, such as client response times for critical decisions, and unavoidable weather disruptions. These variables heavily impact sensitive early-stage work, including land clearing, grading, and concrete foundation preparation and pouring.

Summary of Production Timeline
  1. Engineer Building: Manufacturers documentation for permit application will take 2-4 weeks on average.
  2. Engineer Foundation: *Must have building engineering documents [before] foundation engineering can start. Foundation documentation for permit application will take 2-4 weeks on average.
  3. Building Permit: 1-day to 120-days for a basic steel (storage) building on private land. *No zoning changes/variances required.
  4. Land Clearing: Heavily forested per acre for dozing and grubbing – tree and root removal takes 120+ equipment operator man-hours (varies greatly on conditions, land location, weather conditions and equipment)
  5. Grade and Compact Cleared Land:  Grading and compacting one acre of recently cleared, heavily wooded land typically requires 60+ equipment operator man-hours.
  6. Building Pad Site Prep: 1-5 days to Cut the building pad area, Grade, and Compact.
  7. Delivery to Jobsite: Red Iron Steel Package:  Based on design and engineering complexity, and market conditions, shop fabrication and delivery times can span 16 weeks (minimum) to 20 weeks depending on supply chain variables.
  8. Concrete Foundation: 1-2 weeks to prep, inspect, pour, and finish.
  9. Concrete Curing Phase: 28-days (4-weeks) minimum. Required.
  10. Erection Complete: 2-3 weeks.
  11. Erection: ADD interior build-out, MEP and interior finishing 24-32 weeks.