Timeline: Metal Building Construction | Red Iron 50x100

Production timeline for the turnkey construction of a 5000 square foot, 50x100 red iron pre-engineered metal building in Raleigh NC

Planning, designing, engineering, fabrication, and installation are all provided by Inco Steel Buildings, Inc.

2024 Timeline for professional metal building construction

5000 Square Feet

Pre-Engineered Metal Building, Red Iron I-Beam Steel

Inco Steel Buildings, Inc provides [all] planning, design, engineering, fabrication and installation.
  • 50W x 100L x 16EH PEMB
  • Commercial Grade Steel Building
  • Clear Span.  Red Iron I-Beam Steel
  • 26-Gauge PBR Purlin Bearing Rib Panel
  • 12×14 Rollup Steel Sheet Doors
  • 3070 Steel Hollow Core Personnel Doors

Production Timeline

Red iron metal buildings have a wide range of factors that influence the production timeline when the job is well-planned, organized and erected by skilled professionals. 

Typical factors include the building size, and type, the complexity of the project, the delivery of special-order materials and products, weather conditions, the time of year building is being constructed, and building component specifications. 

Critical factors beyond Inco Steel Buildings, Inc control include the other parties’ timely decision-making, their cooperation during the entire process, their completion of land use and zoning approvals, and their scheduling and supply of land surveyor’s documents and plat plan during the pre-construction phase.

5000 Square Feet Timeline

WORK DESCRIPTION

PROJECTED NO OF WEEKS

AVERAGE

Land Survey Documents and Plat Plan [by the Customer]

4 Weeks Minimum

4.0

Process: Contract Agreement

1-2 Weeks

1.5

Process: Customer Approval of *Inco Concept Design*

1-4 Weeks

2.5

Purchase Order Steel Building Package [Process]

0.75 Week

0.75

Mobilization: Setup Project and Closing of Project

2 Weeks

2.0

Engineer Steel Building Design and Detail

4 Weeks

4.0

Engineer Steel Building Drawings [Final]

2-3 Weeks

2.5

Shop Fabrication and Jobsite Delivery

16-20 Weeks

18.0

Engineer Foundation System

4 Weeks

4.0

File Building Permit Application

0.25 Week

0.25

Zoning Variance by Municipality [When Required]

4 Weeks

4.0

Building Permit by Municipality

Plans Review and Permitting Process: Building

4-20 Weeks

12.0

Site Preparation, Grading and Compacting

2-3 Weeks

2.5

Foundation Preparation

1 Week

1.0

Inspection: Open Foundation by Municipality

Engineering and Building Code Compliance

1 Week

1.0

Pour Foundation

0.25 Week

0.25

Concrete Curing of Foundation [Per Engineer]

4 Weeks Minimum

4.0

Erect Steel Frame and Openings

1-2 Weeks

1.5

Inspection: Steel Frame by Municipality

Engineering and Building Code Compliance

0.5 Week

0.50

Doors and Windows: Install and Water-Proof

1 Week

1.0

Metal Roof, Wall Sheeting (26-Gauge PBR)

1-2 Weeks

1.5

Gutter and Downspout System

1 Week

1.0

Inspection: Building Final by Municipality

0.5-Week

0.50

Issuance of the Certificate of Occupancy by Municipality

4 Weeks Minimum

4.0

Interior Finishing

Not Included

0.0

PROJECTED NO OF WEEKS

45-72 (+/-)

* Zoning Variance Varies by NC county/city. It will take 1-2 days for some counties to approve variances; others will take 1-3 months or longer.

 

*Permit issuance Varies by NC county/city. For most counties, issuance of a building permit takes 1-2 days, while other counties/cities may take months to process.

 

*Inspections Vary by NC county/city. Most inspect in 1 day, sometimes 2 days, other counties/cities may take 5 days or more to inspect.

 

>> PROCESS - FLOWCHART <<